Remodel Estimate Template: Pricing a Kitchen or Bathroom Line by Line

By Brainfy Studio · Published · 9 min read

Construction and trades

Bathroom remodel estimate build-up from labour and materials to a $12,100 total with 10% contingency and a 25% markup, over the estimate sheet of the Residential Construction Estimate Template

A remodel estimate is a list of line items, each priced the same way: labour as hours × rate, materials as quantity × unit cost plus a waste allowance, then permits, allowances for the client's selections and a contingency, with a markup or margin on top. This guide explains each step, gives the markup and margin formulas, and works through one bathroom and one kitchen estimate. Every figure is an illustrative example, not a price for your region.

Free online tool: Construction Estimate Calculator

Build a quick line-item construction estimate with material and labour unit costs, sales tax on materials, overhead, contingency and profit. Runs in your browser; no account needed.

Open the construction estimate calculator

Also useful: Markup Calculator, Home Renovation Budget Calculator

How do you estimate a remodel?

Price every line in the same order, then add the job-level items. The direct cost is what the job costs you; the price is what the client pays.

  1. Labour: hours × hourly rate, for each trade your own crew does.
  2. Materials: quantity × unit cost × (1 + waste %).
  3. Subcontractors: their written quotes, entered as they are.
  4. Permits and fees: the actual or quoted amount.
  5. Allowances: a set amount for fixtures and finishes the client will choose.
  6. Contingency: a percentage of the direct cost for what you cannot see yet.
  7. Markup or margin: applied to direct cost plus contingency to give the price.

Related: Free Construction Estimate Calculator (materials, labour, overhead, contingency and markup in your browser)

How do you price labour?

Labour is hours × hourly rate. Estimate the hours per task from your own past jobs, not from a general guide, and use a loaded hourly rate that covers wages, payroll costs and the time spent travelling and setting up. In the bathroom example below, tile setting is 24 hours × $70 = $1,680.00.

Price each trade on its own line. If a sub gives you a fixed quote, enter the quote rather than converting it to hours.

How do you price materials and waste?

Materials are quantity × unit cost × (1 + waste %). The waste allowance covers cuts, breakage and pattern matching: plain floor tile in a small room might carry 10%, and a wall pattern with many cuts 15%. In the bathroom example, floor tile is 40 sq ft × $7.50 × 1.10 = $330.00.

Use current quotes from your own suppliers, and write the quantity source next to each line (drawing, site measure) so it can be checked.

How do permits, allowances and contingency fit in?

Permits and inspection fees go in at the amount your local authority charges; they vary by place and job size, so look them up for each job. Allowances are amounts for items the client has not chosen yet (vanity, fixtures, cabinets, countertops). Show them as separate lines so the client can see what is included and what a more expensive choice would add.

Contingency is a percentage of the direct cost for problems you cannot see before opening walls and floors. There is no single right figure; older houses and jobs with hidden plumbing usually deserve more. Both examples below use 10% only as an illustration.

Markup vs margin: which formula should you use?

Markup is profit as a share of cost; margin is profit as a share of price. The same profit gives a smaller margin than markup, so be clear which one you mean.

  • Markup % = (price − cost) ÷ cost. Price from a markup = cost × (1 + markup).
  • Margin % = (price − cost) ÷ price. Price from a margin = cost ÷ (1 − margin).
  • To convert: margin = markup ÷ (1 + markup); markup = margin ÷ (1 − margin).
The same $20,000 cost priced two ways
MethodCalculationPriceProfitProfit as % of the other base
25% markup$20,000 × 1.25$25,000.00$5,000.0020.00% margin
25% margin$20,000 ÷ 0.75$26,666.67$6,666.6733.33% markup

Pricing a job at a 25% markup and expecting a 25% margin leaves $1,666.67 of the intended profit out of the price on this job.

Related: Markup vs margin for contractors, with a conversion table · Free Markup Calculator

Worked example: bathroom remodel estimate

A fictional 5 ft × 8 ft bathroom: new floor tile (40 sq ft), a tiled shower surround (80 sq ft), a new vanity, toilet and shower trim, and paint. The client chooses the vanity and fixtures, so they are allowances. Labour rates, unit costs, the permit fee and the quotes are illustrative examples, not regional prices.

Bathroom remodel: line items and totals
LineHow it is calculatedAmount
Demolition and disposal10 h × $65$650.00
Tile setting, floor and shower24 h × $70$1,680.00
Carpentry: vanity, trim, accessories12 h × $65$780.00
Painting6 h × $55$330.00
Floor tile40 sq ft × $7.50 × 1.10 waste$330.00
Shower wall tile80 sq ft × $6.00 × 1.15 waste$552.00
Backer board, membrane, setting materials120 sq ft × $3.50, waste included$420.00
Drywall, paint and trim1 lot × $283.00$283.00
Plumber's quotefixed quote$1,850.00
Permitexample fee$275.00
Allowance: vanity and topclient selection$900.00
Allowance: toilet, tap and shower trimclient selection$750.00
Direct costsum of the lines above$8,800.00
Contingency$8,800.00 × 10%$880.00
Cost before markupdirect cost + contingency$9,680.00
Markup$9,680.00 × 25%$2,420.00
Estimate total (before tax)cost + markup$12,100.00
Margin on price$2,420.00 ÷ $12,100.0020.00%

Labour for the own crew is 52 hours ($3,440.00) and materials with waste come to $1,585.00. A 25% markup gives a 20.00% margin, which is the conversion in the formula section above.

Worked example: kitchen remodel estimate

A fictional 10 ft × 12 ft kitchen: new cabinets and countertop (allowances), luxury vinyl plank flooring (120 sq ft), a tiled backsplash (30 sq ft), new lighting circuits and a relocated sink. The client supplies the appliances. This time the contractor prices for a 25% margin on price instead of a markup. All figures are illustrative examples, not regional prices.

Kitchen remodel: line items and totals
LineHow it is calculatedAmount
Demolition and disposal16 h × $65$1,040.00
Cabinet installation28 h × $70$1,960.00
Flooring installation14 h × $65$910.00
Backsplash tile setting10 h × $70$700.00
Drywall repair and painting16 h × $55$880.00
Vinyl plank flooring120 sq ft × $4.50 × 1.10 waste$594.00
Backsplash tile30 sq ft × $12.00 × 1.15 waste$414.00
Drywall, paint and trim1 lot × $480.00$480.00
Fasteners, adhesives and sundries1 lot × $222.00$222.00
Electrician's quotefixed quote$2,400.00
Plumber's quotefixed quote$1,200.00
Permitsexample fee$450.00
Allowance: cabinetsclient selection$9,000.00
Allowance: countertopclient selection$3,800.00
Allowance: sink and tapclient selection$650.00
Direct costsum of the lines above$24,700.00
Contingency$24,700.00 × 10%$2,470.00
Cost before margindirect cost + contingency$27,170.00
Estimate total (before tax)$27,170.00 ÷ (1 − 25%)$36,226.67
Profittotal − cost$9,056.67
Markup on cost$9,056.67 ÷ $27,170.0033.33%

Labour for the own crew is 84 hours ($5,490.00), materials with waste $1,710.00 and subcontract quotes $3,600.00. A 25% margin needs a 33.33% markup on cost; pricing this kitchen at a 25% markup instead would give $33,962.50, a 20.00% margin.

Related: Turn the estimate into a proposal the client signs

Which template should you use?

To price a job, the free online Construction Estimate Calculator handles materials, labour, overhead, contingency and markup in your browser. For repeat work, the paid Residential Construction Estimate Template lays the same method out by division, and the paid Contractor Professional Estimating System adds a reusable cost item library and a client proposal sheet. Homeowners tracking their own renovation can use the free Home Renovation Budget Calculator or the paid Home Renovation Budget Planner. The spreadsheets are tested in LibreOffice Calc only.

Related: Residential Construction Estimate Template · Contractor Professional Estimating System · Free Home Renovation Budget Calculator

Before you send a remodel estimate

  • Every labour line shows hours × rate, from your own production records.
  • Every material line shows quantity × unit cost and its waste percentage.
  • Permit fees are the current figures for this job's location.
  • Allowances are separate lines with what each one covers.
  • Contingency is written down as a percentage of direct cost.
  • You know whether your profit figure is a markup or a margin, and have checked the other.
  • Exclusions and the items the client supplies are listed.

Brainfy files for this task

Checked against the files customers download. Prices are current catalogue prices.

  • Residential Construction Estimate Template (Paid — $29.99)

    XLSX · 1 file · sheets: Start Here, Estimate

    A line-item estimate by division with material and labour per unit, your labour rate, overhead, contingency, profit and sales tax on materials set once at the top. Its profit percentage is a markup. Paid. Tested in LibreOffice Calc only.

  • Contractor Professional Estimating System (Paid — $148.99)

    PDF + XLSX · 3 files · sheets: Start Here, Company, Item Library, Estimate, Proposal

    Adds a 300-row cost item library (type a code and quantity and the line fills in) and a printable client proposal with scope and exclusions. Paid. The .xlsx is tested in LibreOffice Calc only.

  • Home Renovation Budget Planner (Paid — $18.99)

    XLSX · 1 file · sheets: Start Here, Budget, Lists, By Category

    For the homeowner's side: up to 120 items with estimate, actual cost and paid so far, with totals by category. Paid. Tested in LibreOffice Calc only.

Questions

Are these prices right for my area?

No. Every rate, unit cost, fee and quote on this page is an illustrative example chosen so the arithmetic is easy to follow. Use your own labour rates, supplier quotes and local permit fees.

Should contingency be marked up?

In these examples the markup or margin is applied to direct cost plus contingency, the same way the free calculator applies profit after contingency. Whichever method you choose, use it on every job so your prices stay comparable.

What is the difference between an allowance and contingency?

An allowance is a known item the client has not chosen yet, with a set budget. Contingency covers unknown problems, such as rot found behind a wall. Clients can see and change allowances; contingency is your reserve for the job.

Which apps open the estimate workbooks?

They are .xlsx files. They were recalculated in LibreOffice Calc with no formula errors and checked against expected values; Microsoft Excel, Google Sheets and Apple Numbers were not tested.

Sources and method

Both remodels are invented. Every line (hours × rate, quantity × unit cost × waste), each subtotal, the contingency, the markup and margin figures and both totals are recomputed by an automated test with the same rounding as the free calculators. Product facts were read from each product's live page on November 19, 2026.

Keep going

Related products and free resources

Published Brainfy Studio products for this task. Prices are current catalogue prices.

Free online tools: Construction Estimate Calculator, Markup Calculator, Home Renovation Budget Calculator